Immigration Expansion Project

Project Owner · Not Assigned

StatusActive
HealthDelayed
Actual Project Progress96%

Schedule

Start Date
01 Feb 2026
Target Date
01 Apr 2026
Expected Duration
Not confirmed
Time Elapsed100%
Days Overdue
155
  • 155 days overdue
Current Stage
HandoverConstruction Done
Next Milestone
Arrival queuing area delivery
Key Update / Blocker
Arrival queuing area ordered and expected soon..
Last Update Meaningful project change